From subdivision to keys

How a Tungsten build runs, step by step.

Six stages, in the order that keeps budgets and programmes honest. Here is what we do at each one, and what we will need from you.

  1. Overhead aerial of a new home's slab and framing on a corner section

    01

    Land and feasibility

    We review the title, covenants and consent notices, the Unitary Plan zone and overlays, the survey and geotechnical report, services and access. You find out early what the site allows and what preparing it is likely to cost.

    Your part: Share the address, title and any reports you already have.

    Bought land? What to do next
  2. Kitchen with a thick stone benchtop in a completed home

    02

    Design and pricing

    Working with your architect or designer, or one we introduce, the plans are developed alongside the budget. We give buildability feedback while changes are still cheap, then a written, itemised price with inclusions, exclusions and any provisional sums.

    Your part: Make design and specification decisions so the price can be firm.

    What drives build cost
  3. Aerial of a block of new attached homes under construction

    03

    Contract and consents

    Before you sign, you receive the disclosure statement and the official consumer checklist with the written contract. Resource consent is obtained where needed, then building consent, with council information requests answered promptly.

    Your part: Review the contract with your lawyer and confirm finance with your lender.

    Resource vs building consent
  4. Swimming pool shell and site works under construction

    04

    Site works and foundations

    Site establishment, earthworks, retaining, drainage, service trenches and the foundation or slab, set out accurately and inspected by council before the frame goes up.

    Your part: Stay in touch with progress updates and the first progress payment.

    Site works explained
  5. Builders working on wall framing from scaffolding

    05

    Frame, roof and close-in

    Wall and floor framing, roof trusses and roofing, joinery and building wrap make the house weathertight. Cladding and services rough-in follow, with framing and pre-line inspections booked as each stage is ready.

    Your part: Confirm remaining selections so materials can be ordered on time.

    How long a build takes
  6. Living area opening to the lawn in a completed home

    06

    Fit-out, completion and handover

    Insulation and linings, kitchens, bathrooms, flooring, painting and finishing. After the final inspection we apply for the code compliance certificate, walk through the home with you and hand over warranties and maintenance information.

    Your part: Walk through the home, note anything to fix and receive your keys.

    Your rights after completion

FAQ

Common questions

How often will I hear from you during the build?

You will have a single point of contact and regular progress updates at each stage, plus a programme showing the main milestones. If something changes, we tell you early.

Can I visit the site?

Yes, by arrangement. Building sites are hazardous, so visits are organised with us so we can make sure you are safe.

What happens if I want to change something mid-build?

Changes are handled as variations. We price them in writing before the work goes ahead, and some changes may need a consent amendment.

What do I receive at handover?

Your code compliance certificate once issued, producer statements and warranties for products and systems, and maintenance information for the home.