Resource consent vs building consent: what you need to build in Auckland

By the Tungsten Construction team · Reviewed · 3 min read

Aerial view of a scaffolded block of new attached homes in Howick

The short answer

A building consent checks that the proposed building work will meet the New Zealand Building Code, and almost every new home needs one. A resource consent checks that the use and development of land meets the Auckland Unitary Plan, and is only needed when your project breaks a planning rule or involves subdivision. Some projects need both, and resource consent usually comes first.

Key takeaways

  • Building consent is about the building: structure, weathertightness, fire safety and services.
  • Resource consent is about land use: height, setbacks, site coverage, number of homes, earthworks and subdivision.
  • A new home that meets every planning rule for its zone may not need resource consent at all.
  • Subdivision always needs resource consent in Auckland.
  • Where both are needed, get resource consent first so the building design does not have to change.

“Do I need consent?” is one of the most searched questions before a build, partly because there are two very different kinds of consent. They are issued under different laws, check different things and are often handled by different teams at council.

The short version

Resource consent Building consent
Law Resource Management Act 1991 Building Act 2004
What it checks How land is used and developed How the building is designed and built
Rules it tests against Auckland Unitary Plan New Zealand Building Code
Typical triggers Breaking a zone rule, subdivision, large earthworks Almost all new homes and structural work
Needed for every new home? No Almost always

A building consent confirms that the proposed work will comply with the Building Code, which covers structure, durability, weathertightness, fire safety, access, plumbing, drainage, energy efficiency and more.

For a new home, the application typically includes architectural drawings, structural engineering, specifications, a geotechnical report and drainage plans. Council has 20 working days to decide, with the clock stopping if it asks for more information.

During construction, council inspects the work at set stages. When the work is complete, you apply for a code compliance certificate.

A resource consent is needed when a project does not meet the rules in the Auckland Unitary Plan for your zone and any overlays. Common triggers for residential projects include:

  • building higher than the height limit or breaching the height-in-relation-to-boundary control;
  • building closer to a boundary than the setback rules allow;
  • exceeding the maximum site coverage or impervious area;
  • building more homes than the zone allows without consent;
  • earthworks over the permitted volume or area;
  • building within a flood plain, overland flow path or other overlay;
  • subdividing land, which always needs resource consent.

Applications include an assessment against the relevant rules and often specialist reports. The statutory timeframe for a non-notified application is 20 working days, again paused for further information requests. Notified applications take longer.

When you need both

Many developments and some custom homes need both. Multi-unit projects, for example, often need a land use consent for the homes, a subdivision consent for the new lots, and building consents for each building.

In most cases, it is best to secure resource consent before finalising the building consent drawings. If resource consent conditions change the design, building consent drawings prepared too early may need to be amended.

Where a PIM fits

A project information memorandum (PIM) is a council report about your specific project. It brings together information such as hazards, services, heritage and whether development contributions apply. It is not a consent, but it can flag issues early. A PIM is mandatory for granny flats built under the building consent exemption.

Recent changes worth knowing

  • Granny flats. Since 15 January 2026, certain single-storey standalone dwellings up to 70 m² can be built without building consent, subject to strict conditions. See our granny flat guide.
  • Inspections. Since August 2025, building consent authorities have been required to complete most inspections within three working days.
  • Auckland zoning. Plan Change 120 is changing where more intensive housing is allowed. Final decisions are expected in 2027, so check the current rules for your address.

How we help

On our projects we coordinate consent documentation with your designer and engineers and respond to council requests for information during processing. Tell us about your project and we can help you work out which consents are likely to be needed.

Frequently asked questions

Do I need resource consent to build a house in Auckland?

Not always. If the house complies with all the rules for your zone and any overlays, such as height, setbacks, coverage and earthworks limits, no resource consent is required. If it breaks a rule, or you are subdividing, you will need one.

Can I apply for building consent and resource consent at the same time?

You can lodge them in parallel, but building consent cannot be issued in a way that conflicts with an outstanding resource consent. Many people get resource consent first so the building drawings reflect the final consented design.

What is a PIM?

A project information memorandum is a council report on a specific proposed project. It sets out relevant information such as hazards, services and whether other approvals or development contributions may apply. You can apply for one before or with your building consent.

Do granny flats need consent?

Since 15 January 2026, some small standalone dwellings up to 70 m² can be built without building consent if strict conditions are met, but a PIM is still required. Our granny flat guide explains the conditions.

Sources and further reading

  1. Resource consents (Auckland Council)
  2. Building consents (Auckland Council)
  3. Building consent process, building.govt.nz
  4. Project information memoranda (PIMs), building.govt.nz
  5. Auckland Unitary Plan online viewer

This guide is general information for New Zealand, current at the review date above. Rules and council requirements change, so check your own situation with the relevant council, your lawyer or other qualified adviser before relying on it.